At last night's Girdwood Board of Supervisors meeting Agnew::Beck Consulting and Anchorage Water and Wastewater Utility presented information about an upcoming project. Our existing wastewater treatment plant, constructed in 1978, needs to be replaced. This is a $40M - $60M project to be paid for by all A. W. W. U. customers and could be eligible for stimulus money. A. W. W. U. is seeking approval by this summer, with design, bid, and construction completed by 2014. Construction is anticipated to take two years.
For more information, see the Agnew::Beck website at the end of this month at www.AgnewBeck.com . Also look for Agnew::Beck and A. W. W. U. to make appearances at the Land Use Committee and again at the Board of Supervisors in March and/or April.